As part of the renovation of the Budapest Chain Bridge, the first renovated part has already been painted with a true to the original blue-gray color. In addition, the demolition of the underpass has also begun.
This article was originally posted on our sister-site, Ungarn Heute.
Within the framework of the project, the corrosion protection of a total area of more than 23 thousand square meters is carried out, proceeding with the work from top to bottom.
Demolition of the underpass on the Buda side has also begun so that a larger and safer underpass can be built in its place: A four-meter-wide tunnel with vertical walls will be built in place of the former three-meter-wide bicycle tunnel, so that a sidewalk will also be constructed in addition to the two-directional bicycle path.